PROJECT
Landlord Spec Improvements
- Full site concrete paving, no asphalt used
- Reinforced concrete truck aprons
- Warehouses are evaporative cooled with 3 air exchanges per hour
- Warehouses are equipped with LED lighting measuring 20 foot-candles at 36” above finished warehouse floor
- Pre-installed conduit for future truck court motorized gates
- 35,000 lb mechanical dock levelers at every other dock-high door
FULL SITE PLAN
BLDG 2
SITE PLAN

BUILDING 1
9530 S RAINBOW BLVD
±57,519 SF
TOTAL SF
±2,430 SF
1ST STORY
OFFICE AREA
±1,860 SF
2ND STORY
OFFICE AREA
CLEAR HEIGHT
32' clear from first column
DOCK DOORS
5 (9' x 10')
GRADE DOORS
1 (12' x 14')
TRUCK COURT
±132’ with 60’ concrete apron
AUTO PARKING
84
COLUMN SPACING
50’ x 52’ with
60’ speed bay
POWER
2,000 A, 277/480 V,
3-Phase (expandable)
SPRINKLER
ESFR
ROOFING
60 mil TPO
ROOF INSULATION
R-19
FLOOR SLAB
6” concrete slab min

BUILDING 2
9560 S RAINBOW BLVD
±79,325 SF
TOTAL SF
±2,352 SF
1ST STORY
OFFICE AREA
±1,783 SF
2ND STORY
OFFICE AREA
CLEAR HEIGHT
32' clear from first column
DOCK DOORS
8 (9' x 10')
GRADE DOORS
2 (12' x 14')
TRUCK COURT
±132’ with 60’ concrete apron
AUTO PARKING
79
COLUMN SPACING
50’ x 52’ with
60’ speed bay
POWER
2,000 A, 277/480 V,
3-Phase (expandable)
SPRINKLER
ESFR
ROOFING
60 mil TPO
ROOF INSULATION
R-19
FLOOR SLAB
6” concrete slab min

BUILDING 3
9590 S RAINBOW BLVD
±83,153 SF
TOTAL SF
±2,354 SF
1ST STORY
OFFICE AREA
±1,775 SF
2ND STORY
MEZZANINE
CLEAR HEIGHT
32' clear from first column
DOCK DOORS
14 (9' x 10')
GRADE DOORS
2 (12' x 14')
TRUCK COURT
±129’ with 60’ concrete apron
AUTO PARKING
80
COLUMN SPACING
50’ x 52’ with
60’ speed bay
POWER
2,000 A, 277/480 V,
3-Phase (expandable)
SPRINKLER
ESFR
ROOFING
60 mil TPO
ROOF INSULATION
R-19
FLOOR SLAB
6” concrete slab min

BUILDING 4
6885 GARY AVE
±36,493 SF
TOTAL SF
±2,241 SF
1ST STORY
OFFICE AREA
±1,665 SF
2ND STORY
MEZZANINE
CLEAR HEIGHT
28' throughout
DOCK DOORS
4 (9' x 10')
GRADE DOORS
1 (12' x 14')
TRUCK COURT
±130’ with 60’ concrete apron
AUTO PARKING
38
COLUMN SPACING
50’ x 52’ with
60’ speed bay
POWER
1,000 A, 277/480 V,
3-Phase (expandable)
SPRINKLER
ESFR
ROOFING
60 mil TPO
ROOF INSULATION
R-19
FLOOR SLAB
6” concrete slab min

BUILDING F
F: 8241 W BADURA AVE

82,094 SF
+2,455 SF
PROPOSED
OFFICE
12 DOCK
DOORS
6 GRADE
LEVEL DOORS
83 PARKING
SPACES
9 TRAILER
PARKING STALLS
180' CONCRETE
TRUCK COURT
(shared)